Configure the Calibration Group

  1. Go to: Shop Floor Control > Config > CMMS Admin > Group.
  2. Add a new Calibration Group or edit an existing Calibration Group.
  3. Select the Calibration Categories at the General tab as needed.
  4. Go to the Users tab and add Users one at a time.

Screenshot: Set Group Category

1 Group.png

 

Screenshot: Add Group’s Users

Add group user.png

 

Assign the Calibration Group to Assets

 

  1. Go to: Shop Floor Control > Config > CMMS Asset and select the Asset to edit .
  2. Add Calibration Categories to this Asset's Group:
  3. Go to Group Tab.
  4. Add Calibration Categories one at a time.

 

Screenshots: Set Calibration Category

Calibration category.png

 

Screenshot: Set Group for Asset

Assign group to asset.png

Assign the Calibration.

  1. At the Edit Asset Page,move to the Asset’s Calibration Tab.
  2. Complete the following mandatory fields:
  • Calibration Needed checkbox.
  • Last Calibration Date
  • Interval (mth)
  • system will populate Next Calibration Date based on the Last Calibration Date, and the number of months selected in the Interval section.
  • Grace Period(Days).
  1. Complete the other optional fields if needed.
  2. Save.

Screenshot: Edit Asset Calibration Tab

Calibration tab.png

 

  1. Email notification goes to the Assigned group members, including Requester and Approver.

 

Screenshot: Assigned Alter Email

Assigned Alter Email.png

Complete the Calibration on the Asset

  1. Go to:Production > CMMS Calibration > My Assigned.
  2. Double click on theAsset Name.
  3. Fill out the following mandatory fields:
  • Input Status
  • Actual Calibrated Date

Note: Only the Input Statu be set to Complete - Approval, this calibration Asset’s go to the approval process.

  1. Fill out other optional fields if needed.
  2. Save.

Screenshot: Calibration Assigned

Calibartion Assigned.png

 

  1. Email notification goes to the Approver and the assigned group members (this person was selected when the Calibration need approver) (Step 2).

 

Screenshot: Status Change alter Email

Status Change Alter Email.png

 

Approve (or Reject) the Calibration

  1. Go to: Production > CMMS Calibration > My Approvals.
  2. Double click on the Asset Name.
  3. Complete the following mandatory fields:
  • Input Status: Select Approved or Rejected.
  • Actual Cal Date .
  1. Save.

Screenshot: Calibration Approval

Calibration approval.png

  1. An email notification goes to the approver, requester, and assigned group members.

 

Screenshot: Approval Alter Email

Approval alter email.png

 


Reschedule the Calibration

  1. Go to:Production > CMMS Calibration > My Rescheduling.
  2. Double click on the Asset Name.
  3. Complete the following mandatory fields:
  • Rescheduled Date.
  1. Save.

Screenshot: My Rescheduling

Calibration rescheduled.png

 

 

 


Revision Log

Revision # Revision Date Description Updated by Approved by
1 12/19/18 Initial Draft Martha Jordan  
1 4/11/19 Update screenshots. Correct some mandatory fields Add Reschedule section Helena Wang